The dispute over the modernization of energy infrastructure in southern Gran Canaria has been resolved following the revision of the technical criteria applied to the transmission network. The litigation, which stemmed from the conditions imposed on the electricity distributor for updating access permits, was formally settled after the national electricity system operator amended its initial proposal and removed the restrictions related to high-voltage load capacity.
The conflict pitted the distribution company against the transport network manager following a request to replace two 30 megavolt-ampere (MVA) transformers with 40 MVA equipment at the Lomo Maspalomas 66 kilovolt (kV) substation, located in the municipality of San Bartolomé de Tirajana.
The disagreement arose when the operator initially demanded that the distribution network assume one hundred percent of the backup to the transport network in cases of technical unavailability, a requirement that the distributor considered inappropriate as it was a meshed node and would overload local suppliers with improper responsibilities.
Following the formal filing of the regulatory dispute, the network operator reviewed the file and issued the final access and connection permits after confirming that the initial proposal contained a technical error. Since the substation has a meshed configuration and multiple feeds, the competent authority acknowledged that it was not appropriate to require preferential maintenance periods or to transfer to the distributor the full backup obligations typical of simple radial nodes.
This administrative correction has led to the eventual disappearance of the controversy, as the distributor's demands have been met, allowing the modernization of the transformers to be unblocked in a strategic location for the economic and tourist development of southern Gran Canaria.