Las Palmas bypasses the south of Gran Canaria and gives the green light to the 14 power line poles between Santa Águeda and El Tablero
Panoramic view of El Tablero de Maspalomas Panoramic view of El Tablero de Maspalomas

Las Palmas bypasses the south of Gran Canaria and gives the green light to the 14 power line poles between Santa Águeda and El Tablero

Gara Hernández - M24h Tuesday, October 27, 2026

 

The Ministry of Ecological Transition and Energy of the Government of the Canary Islands has issued the resolution granting the administrative authorization and the declaration, specifically, of public utility to the electric transport project called '66 kV overhead-underground electric power transport line, single circuit, Santa Águeda - El Tablero 2', promoted by the entity Red Eléctrica de España, SAU in the municipality of San Bartolomé de Tirajana. 

This strategic infrastructure project has an execution budget of €4.639.283 and aims to strengthen the grid and security of the energy supply in the south of Gran Canaria. The project, registered under reference AT23/015, involves the development of a route with a total length of 10,304 kilometers. Of this total distance, 5,233 kilometers correspond to an overhead section equipped with a 66 kV circuit using AL/AW HAWK type conductors and supported by 17 metal pylons, sequenced from T-1 to T-17. 

The remaining 5,071 kilometers will be laid via underground conduit, divided into two distinct sections. The first section runs for 167 meters from the Santa Águeda substation to the T-1 transition support, while the main underground section covers approximately 4.904 meters. This latter section crosses roads and strategic locations such as Mar de Azor Street, Avenida de la Unión Europea, the Tabaquera ravine, the underpass beneath the GC-1 highway via Doctor Agustín Millares Carlo Street and Francisco Vega Monroy Avenue, and Chile and Cartago roads, before connecting to the El Tablero substation.   

During the mandatory public information process, published in the official bulletins and in various island newspapers, multiple allegations were made by commercial companies, water management entities and large landowners, among which Elmasa Tecnologías del Agua, Invercasti Alfa, Herederos de Alejandro del Castillo Bravo de Laguna, Propiedades Mejoradas and the Tinojai Real Estate Group stand out. 

The objections focused on correcting property ownership records, delimiting areas affected by easements, and demands for the complete undergrounding of the power line route. The developer, Red Eléctrica, responded to the interested parties, arguing that the route complies with the binding plan for the transmission network and that the declaration of public utility justifies the need for land occupation. However, the company expressed its full willingness to coordinate technical surveys, study specific impacts, and agree on fair compensation for any damages caused.   

At the institutional and sectoral level, the San Bartolomé de Tirajana City Council issued unfavorable reports regarding the underground section due to its impact on the municipal road network in urban and developable land, although it gave its approval to the overhead route within the framework of the current urban planning (PGOU'96). 

For its part, the Directorate General for Natural Spaces and Biodiversity warned of the presence of habitats of community interest and the need to protect birdlife in the scrubland and thermomediterranean thickets. Likewise, operators such as Canaragua and Telefónica issued technical conditions regarding the protection of their basic services and telecommunications networks during trenching and cable laying work.   

The project's environmental viability was confirmed by the General Directorate of Environmental Quality, which determined that the project would not generate significant adverse effects provided that strict preventative conditions were met. The environmental annex mandates the prior drafting of a Logistics Organization and Coordination Plan to minimize the project's time footprint and optimize the use of heavy machinery. 

Similarly, given the risk of collisions with protected birds, the installation of advanced triple-blade catadioptric anti-collision devices with ultraviolet beacons is mandatory on the overhead section. Furthermore, a bi-weekly and monthly monitoring protocol for bird collisions must be established throughout the installation's lifespan, overseen by the Environmental Agents of the Gran Canaria Island Council. Finally, the developer must complete a Geomorphological Restoration and Revegetation Plan using native species to ensure the full landscape integration of the affected slopes, access points, and storage areas.

 