The San Bartolomé de Tirajana City Council has initiated a procurement process for the complete renovation of municipal playgrounds. The project, managed by the Parks and Gardens Department, includes the supply, installation, and anchoring of new play equipment, such as swings, slides, and play structures, along with the installation of artificial turf safety surfacing with a shock-absorbing base. The work will be carried out in various recreational areas throughout the southern town, based on the deficiencies identified by municipal services.

The design and layout of these public spaces are governed by strict technical parameters divided into four main zones. The Play Area defines the physical space occupied by the structure and its parts in contact with the ground. The Free Area is the essential zone for users to use the equipment without obstacles; its size varies depending on the type of use, requiring a 1-meter radius around equipment where the user stands or sits, and a 50-centimeter radius around equipment where the user hangs. The Fall Area encompasses the perimeter where children are likely to fall during dynamic play, while the Safety Area defines the maximum surrounding perimeter without obstacles.

The spatial compatibility between these zones establishes strict regulatory criteria regarding their overlap. The fall protection area and the safety area can share space in a complementary way, as they are designed for accident prevention without functional interference. In contrast, the free area and the play area cannot overlap with any surrounding areas under any circumstances and must remain completely clear of obstacles to guarantee the safe movement of children.

The technical specifications justify not dividing the contract into lots because there is an unavoidable functional link between the supply of the equipment and the installation of the protective flooring. Both services require joint certification to strictly comply with European regulations regarding critical fall heights and impact absorption, which prevents technical malfunctions and clearly defines the responsibility for execution.

The contract will be awarded through a standard open procedure, using only the most economically advantageous offer as the criterion for evaluating the proposals submitted. The selected inverse proportionality formula guarantees competitive bidding and prevents distortions, establishing penalties for failure to comply with the proper environmental management of waste generated during the works. The total execution period set for completing the installation of the equipment is four months from the date the contract is formalized.

 