Environmental authorization and coastal occupation for the drainage pipeline of the Puerto Rico WWTP in Mogán

Environmental authorization and coastal occupation for the drainage pipeline of the Puerto Rico WWTP in Mogán

Yurena Vega - M24h Friday, 14 of August of 2026

 

The tourist municipality of Mogán is moving forward with the regularization of its essential water infrastructure through a significant administrative process for the southern coast of Gran Canaria. The General Directorate of Environmental Quality has issued an official resolution opening a public consultation period for the file concerning the authorization for land-based discharge into the sea and the corresponding concession for the occupation of public maritime-terrestrial land directly linked to the drainage pipeline of the Puerto Rico Wastewater Treatment Plant, formally registered under file number VM-044-LP.

This administrative procedure has its roots in the initial request submitted by the Mogán City Council, which on October 15, 2024, formally requested the joint processing of the authorization for land-based discharges into the sea (AVM) and the concession for occupation of the public maritime-terrestrial domain (CODPMT) from the relevant authorities. The infrastructure covered by this file is vital to guarantee the proper treatment, disposal, and purification of wastewater generated in one of the most important tourist and residential areas of the region, ensuring that the operation of the sanitation network strictly complies with the legal and environmental requirements in force in the archipelago.

The technical and legal complexity of this type of sanitation infrastructure requires strict compliance with state and regional regulations concerning coastal areas and environmental protection. In this regard, the procedure is governed by Article 152, sections eight and nine, of the General Coastal Regulations, approved by Royal Decree 876/2014 of October 10. These regulations mandate that the processing of both concessions and authorizations related to industrial and polluting discharges from land into the sea must be subject to a mandatory public consultation process for a minimum period of twenty days.

The regional department has formally decided to submit the file to a non-extendable public consultation period of twenty working days. This period will begin the day after the official publication of the resolution in the Official Gazette of the Canary Islands, thus opening a crucial window for administrative transparency and citizen participation.

To ensure maximum accessibility and allow for detailed consultation by any interested citizen, group, entity, or administration, the complete technical documentation of the file is available to the public in digital format. Once officially published, interested parties can download all reports and plans via the electronic notice board at the headquarters of the Ministry of Ecological Transition and Energy of the Government of the Canary Islands, as well as through the direct download link provided on the regional government's online platforms.

This public consultation period gives residents, environmentalists, social groups and economic agents in the area the opportunity to examine the technical details of the Puerto Rico WWTP drainage pipeline, verify the characteristics of the planned occupation of the public maritime-terrestrial domain and, where appropriate, draft and submit any allegations, observations or technical reports they deem appropriate in defense of the general interests and the preservation of the Mogán coastline.

 